Connecting Elektrilevi OÜ to Kehra 110/35/10 kV substation



Location

Description of work

Other

Status

Time of completion


Buildings
Civil engineering
Concrete works

One new 110 kV cell and commercial metering point was built at the Kehra 110/35/10 kV substation as part of connecting Elektrilevi OÜ to the substation via the new Kehra–Kose 110 kV overhead line. The infrastructure was designed and built and handed over to the customer in ready form.

On 1 July 2021, Merko Ehitus Eesti acquired a stake in Connecto Eesti, and the Merko electrical construction business line merged with Connecto. Acting jointly under the Connecto brand makes it possible for us to offer a significantly broader range of services – in addition to the design, construction and maintenance of low, medium and high voltage electricity networks, Connecto also operates in the field of telecommunications and gas networks.

View the works performed by Connecto.

Client:
Elering AS
Name of the project:
Connecting Elektrilevi OÜ to Kehra 110/35/10 kV substation
Category:
Civil engineering
Type of construction:
Power infrastructure
Chief Designer:
AS Merko Infra and AS Merko Ehitus Eesti
Description of work:
New building
Country:
Estonia
Address:
Paasiku village, Anija rural municipality, Harju County
Beginning of the project:
2015
Year of completion:
2016