Construction of drinking water treatment complex in JūrmalaKauguri, Jurmala

Total length of water and sewerage nets 1,685 m, two water reservoirs (capacity 508 m3 each) and three new artesian wells with pumps were built. Capacity of water iron removal plant – 6,500 m3/d.

Client:
Jūrmalas Ūdens Ltd.
Name of the project:
Construction of drinking water treatment complex in Jūrmala
Category:
Civil engineering
Type of construction:
Water treatment
Designer:
JSC E. Tīlgalis and Partners
Description of work:
New building
Country:
Latvia
Address:
Kauguri, Jurmala
Beginning of the project:
2005
Completion year:
2006
Characteristic feature:
Total length of water main and sewerage network 1,685 m