Construction of the foundations for Šilute wind farmŠilutė district, Usėnų village

Foundations for 24 wind turbines will be built, of which 10 are ordinary foundations and 14 are supported on piles. Merko’s contracts cover excavation, concrete and pile driving work. The entire work must be performed in a short period of time; each week, at least 800-1,000 m3 of concrete will be installed; and each day, 15-20 tonnes of rebar.

Client:
GE wind energy GmbH
Name of the project:
Construction of the foundations for Šilute wind farm
Category:
Civil engineering
Type of construction:
Power infrastructure
Description of work:
New building
Country:
Lithuania
Address:
Šilutė district, Usėnų village
Beginning of the project:
2015
Completion year:
2015
Characteristic feature:
13,220 m3 of concrete; 1423.2 tonnes of rebar