At the Püssi substation of 330/220/110/20/10 kV, there will be built a cell of 110 kV and a commercial measuring point for connecting a new transformer of Elektrilevi Ltd. to the substation.
The project will be completed as a turnkey solution, i.e. the equipment in the scope of the project is supplied together with the necessary design works, will be installed, tuned, checked and finally delivered to the client in energised state.
On 1 July 2021, Merko Ehitus Eesti acquired a stake in Connecto Eesti, and the Merko electrical construction business line merged with Connecto. Acting jointly under the Connecto brand makes it possible for us to offer a significantly broader range of services – in addition to the design, construction and maintenance of low, medium and high voltage electricity networks, Connecto also operates in the field of telecommunications and gas networks.
View the works performed by Connecto.
- Client:
- Elering AS
- Name of the project:
- Connecting Elektrilevi OÜ to Püssi 330/220/110/20/10 kV substation
- Category:
- Civil engineering
- Type of construction:
- Power infrastructure
- Chief Designer:
- AS Merko Infra
- Description of work:
- New building
- Country:
- Estonia
- Address:
- Lüganuse, Ida-Virumaa
- Beginning of the project:
- 2019
- Year of completion:
- 2020