The goal of the expansion of the 330/220/110/35/10kV Kiisa substation, fully renovated in 2010, was to establish connections for the new 250 MW Kiisa emergency power plant. The contract called for one 330kV duplex cell, one 110kV simplex cell and two 10kV local power plant cells to be designed and constructed. The new power plant will start to feed the Estonian power grid at a 140 MW capacity through the 330kV cell and the 110kV cell will feed the grid at 110 MW capacity. The construction work took place in a substation with live equipment, due to which great emphasis was placed on planning the work and worker safety. The cell construction work included earth moving, laying foundations and subframes for the equipment, installation of equipment, connecting of cables and configuration and connections with the existing substation. Two separate 12 m² lightweight panel buildings along with cable basements were built for the plant’s own 10kV equipment.
On 1 July 2021, Merko Ehitus Eesti acquired a stake in Connecto Eesti, and the Merko electrical construction business line merged with Connecto. Acting jointly under the Connecto brand makes it possible for us to offer a significantly broader range of services – in addition to the design, construction and maintenance of low, medium and high voltage electricity networks, Connecto also operates in the field of telecommunications and gas networks.
View the works performed by Connecto.
- Client:
- AS Elering
- Name of the project:
- Construction of Kiisa substation 10kV, 110kV and 330kV connection points
- Category:
- Civil engineering
- Type of construction:
- Power infrastructure
- Description of work:
- Reconstruction
- Country:
- Estonia
- Address:
- Tõdva village, Saku, Harjumaa
- Beginning of the project:
- 2012
- Year of completion:
- 2013