Emajõgi and Võhandu river basin water resources management project; Emajõgi sub-project. Phase II of design and construction work on water and sewerage infrastructure. Part 1: Water and sewerage infrastructure in Nõo municipality



Buildings

Civil engineering

Energy supply

Concrete works


Location

Description of work

 

 

 


6.2 km of water pipelines;
7.2 km of sewerage pipelines;
1.3 km of pressurized sewerage pipelines;
2 new waste water treatment stations: Tõravere 28.7 m³/d, 221 PE, Nõgiaru 15 m³/d, 115 PE;
1 renovated waste water treatment station: Luke 21.5 m³/d, 165 PE;
3 waste water tanks: Tõravere 30 m³; Nõgiaru 20 m³; Luke 20 m³;
4 water treatment stations: Tamsa 1.8 m³/h, 43 m³/d, Etsaste 1.8 m³/h, 43 m³/d, Meeri 1.8 m³/h, 43 m³/d, Tõravere 1.8 m³/h, 43 m³/d;
1 bore well pumping station: Tõravere 8 m³/h;
2 waste water pumping stations: Tõravere 5 l/s (18 m³/h), Nõgiaru 5 l/s (18 m³/h).

Client:
AS Emajõe Veevärk
Name of the project:
Emajõgi and Võhandu river basin water resources management project; Emajõgi sub-project. Phase II of design and construction work on water and sewerage infrastructure. Part 1: Water and sewerage infrastructure in Nõo municipality
Category:
Civil engineering
Type of construction:
Water and sewerage pipelines, storm water drain lines
Description of work:
Reconstruction
Country:
Estonia
Address:
Nõo parish, Tartumaa
Beginning of the project:
2009
Year of completion:
2010