Enefit connection at Illuka 110kV substation



Buildings

Civil engineering

Energy supply

Concrete works


Location

Description of work

 

 

 


One 110kV line cell at Illuka substation for connecting Enefit Kaevandused AS, with a commercial metering system.

Client:
Elering AS
Name of the project:
Enefit connection at Illuka 110kV substation
Category:
Energy supply
Type of construction:
Substations
Designer:
AS Merko Infra
Description of work:
New building
Country:
Estonia
Address:
Ohakvere village, Illuka rural municipality, Ida-Virumaa
Beginning of the project:
2017
Year of completion:
2018