Reconstruction of Hundipea harbor quays No. 8 and 9 and breakwater


The contract scope includes the reconstruction of the mooring lines S8 and S9 of Hundipea Harbor. On the port basin side, the new piling walls will be dredged along the new quay line, in front of which the port basin will have a water depth of 6 or 10 meters. On the seaside, tetrapod shore protection will be built.

  • Quays’ length 26.8 m
  • Draft up to 10 m
  • Breakwater length 183 m
  • Dredging capacity 36,500 m3
  • Tetrapods 3,600 pcs
Client:
Veeteede Amet (Maritime Administration)
Name of the project:
Reconstruction of Hundipea harbor quays No. 8 and 9 and breakwater
Category:
Civil engineering
Type of construction:
Port facilities
Designer:
OÜ Est-Konsult
Description of work:
Reconstruction
Country:
Estonia
Address:
Lume str 9, Tallinn
Beginning of the project:
2018
Year of completion:
2020