- A fully automated drinking water treatment plant with 2 x 150 m³ tanks was built
- 2 bore well pumping stations with automated systems were rebuilt, output of up to a max. 18 m³/hour
- 1 waste water pumping station with automated systems
- 635 m of pipelines between bore well pumping stations, water treatment plant and city public water supply system
- 335 m of sewerage pipelines
- A water tower no longer in use was demolished
- The new plant was designed and built with the purpose of meeting the water consumption needs of 2,560 people
- Client:
- Saarde Vallavalitsus (Saarde Municipality Government)
- Name of the project:
- Water treatment plant of Kilingi-Nõmme
- Category:
- Civil engineering
- Type of construction:
- Water treatment
- Description of work:
- New building
- Country:
- Estonia
- Address:
- Kilingi-Nõmme, Pärnumaa
- Beginning of the project:
- 2012
- Year of completion:
- 2012