Kasutad veebilehitsejat, mida tootja enam ei uuenda. Palun vaheta veebilehitsejat või laadi turvaliseks internetikülastuseks ja meie veebilehe sisu õigesti nägemiseks alla uuem brauser:

Cables of 110 kV of Emajõe substation



Buildings

Civil engineering

Energy supply

Concrete works


Location

Description of work

 

 

 


In May 2007 the cable line of 110 kV installed between the substations of Emajõe and Ülejõe in Tartu was given over to the Client. During the procurement the cable lines of 110 kV were designed and installed to the substation of Emajõe and Ülejõe and between the existing overhead line and the substation of Emajõe. Also, the optical communication cable and the cables of 110 kV of Jaotusvõrk were installed to the same mineral raw material with the cables of 110 kV. About 2.5 km of overhead line was renovated and taken over to the current of 110 kV.

Client:
OÜ Põhivõrk
Name of the project:
Cables of 110 kV of Emajõe substation
Category:
Civil engineering
Type of construction:
High voltage networks – power cables and overhead lines
Description of work:
New building
Country:
Estonia
Address:
Tartu
Beginning of the project:
2005
Year of completion:
2007