• Tondi International Tennis Centre

    Merko’s assignment was to build a parking lot, training halls, weight room, aerobics and massage rooms, lobby, dressing rooms, saunas and spa.


  • Enefit 280 pipe bridge for Eesti Energia Oil Industry

    The Enefit 280 pipe bridge is a support structure for a gas and liquid fuel main pipeline. 1/6 of the total volume of the pipe trestle foundations was formed by a pile cap on piles, the rest of the foundations rest on suppor- ting limestone layers 0.7-2.0 metres deep. For the part of pipe trestle …


  • Power lines of Eesti Energia Oil Industry

    Cable ladders on a reinforced concrete foundation, metal frame, including two substations, roads and lots. On 1 July 2021, Merko Ehitus Eesti acquired a stake in Connecto Eesti, and the Merko electrical construction business line merged with Connecto. Acting jointly under the Connecto brand makes it possible for us to offer a significantly broader range of services …


  • Airplane maintenance facility for the Tallinn Airport

    The airplane maintenance facility of the Tallinn Airport consists of an airplane maintenance hangar in the centre of the facility, and office, storage and workshop areas on three sides. The building stands on socket-type footing on limestone. In places the socket-type footing has been anchored using tension piles. The main building material was prefabricated reinforced …


  • Condensation area of Eesti Energia Oil Industry

    Reinforced concrete platforms as a base for equipment on a metal frame supported by pilings. The facilities include a substation and underground cableways running along reinforced concrete ducts. On 1 July 2021, Merko Ehitus Eesti acquired a stake in Connecto Eesti, and the Merko electrical construction business line merged with Connecto. Acting jointly under the Connecto brand …


  • EE emergency reserve power plants, 110 MW and 140 MW

    A total of four reinforced concrete buildings – two generator buildings and two control buildings, plus 110 kW and 330 kW substations, a tank farm of 14,000 m3, refuelling station and roads and lots. On 1 July 2021, Merko Ehitus Eesti acquired a stake in Connecto Eesti, and the Merko electrical construction business line merged with Connecto. …


  • AS Tallegg production factory

    The renovation work performed by Merko Infra in the existing areas in the Tallegg complex encompassed 1,800 m² while the construction of the addition added 5,000 m² of space. The renovation of part of the Tabasalu plant and construction of the addition were rendered complicated in the construction sense by the fact that the existing …


  • KTN Tallinn Logistics Centre

    Construction of the Katoen Natie Logistics Centre began in February 2013 and the work was delivered in September of the same year. The contract covered the establishment of a warehouse building on a reinforced concrete foundation, with sandwich type wall panels on a metal frame and a weight-bearing sheet metal roof, including a railway spur. …